It is the best technique to develop estimates for your project. There are three steps:
- Identify the positive and negative risks involved in the project
- Then make three estimates — Best Guess (BG), Pessimistic (P), and Optimistic (O) estimates
- The final step is to calculate the mean and standard deviation using the formulas: (O+4BG+p)/6 and P – O/6 respectively.